Location

Miami, Florida.

Area

23,000 ft2

The 3S Team designed MEP system for Office in the city of Miami. 

3S MEP provided the following MEP engineering services. See below for further details

HVAC :

1. Ventilation design as per ASHRAE 170 (2013).
2. Engineered existing AHU unit secondary ductwork distribution as required.
3. Heat load calculation with the help of HAP 5.1.

PLUMBING :

1. Sanitary and kitchen waste as per architecture layout and connected to an existing system.
2. Engineered domestic water supply system.

ELECTRICAL :

1. Electrical riser diagram.
2. Lighting, power, and fire alarm design.
3. Electrical site plan.
4. Electrical panel schedules.
5. Larger conduit modelling.
6. Com-check.
7. Edit electrical details.
8. Create/Edit Revit electrical families.
9. Automatic circuiting.
10. Specification editing.
11. Emergency layout and exit sign layout.
12. Coordination power requirement with another discipline.